    Houghton and Ft. Lowell Intersection
    Project Cost to Date: $882,939
    Project Status: Under Construction
    Completion Date: May  2023
    Engineer/Contractor: Southern Arizona Paving Company 

    The Pima County Department of Transportation along with their contractor, Southern Arizona Paving Company, will begin the realignment construction project of Fort Lowell Road and Houghton Road. The Contractor will begin mobilizing equipment February 6, 2023. 

    The project includes widening a half-mile of Houghton Road to add new turn lanes and reconstructing 450 feet of Fort Lowell Road to realign the roadway and remove the existing intersection offset. Signing and striping improvements will be minimal.

    This project is expected to be completed by May 1, 2023. The hours of operation will be from 6:00 a.m. to 4:00 p.m.



    Email DOT: Fort Lowell/Houghton Rd. Comments

    Community Relations

    Katrina Noble
    Program Manager
    Department of Transportation
    (520) 724-6576
    email: Katrina Noble

    Transportation Engineering

    Shawn Tillson
    Project Manager, Capital Program Office
    Department of Transportation
    (520) 724-6710
    email: Shawn Tillson

    Project Documents


    Follow UsShare this page
    Transportation

    Kathryn Skinner, P.E.
    Director

    201 N. Stone Ave., 4th Fl.
    Tucson, AZ 85701

    Phone: (520) 724-6410
    Fax: (520) 724-6439


    Department Home Page
    Department News
    Department Directory
    Feedback
    Boards, Commissions and Committees
    Report a problem
    Permitting
    Public Works Quick Guide
    Maps
    Volunteer with Pima County
    Volunteer