  • **UPDATE**: VALENCIA ROAD - WADE ROAD TO AJO WAY IMPROVEMENT PROJECT

    Jun 02, 2020 | Read More News
    Share this page

    Valencia Road Improvement ProjectOn Tuesday, June 2 through Friday, June 19, between the hours of 6:30 a.m. and 3:30 p.m., Pima County Department of Transportation and its contractor, The Ashton Company, Inc., will be performing paving activities on the Valencia Road project.

    June 2 through June 4: Work will consist of paving the final lift of the westbound lanes (north side of the road) of Valencia Road beginning at the east end of the project. Temporary striping will follow shortly after.

    June 5 through June 10: Work will consist of paving the final lift of the eastbound lanes (south side of the road) of Valencia Road followed by temporary striping.

    June 11 through June 16: Work will consist of paving the final lift of the side streets and turn bays.

    Please approach the area with caution and obey all traffic control devices. Minor delays may occur during this work. 

    In the event of mechanical failure or inclement weather, the construction schedule is subject to change.