Phase 1
Phase 1 Status: Complete
Phase 1 construction includes the southern extension of Raytheon Parkway and Rocketeer Drive.
Intersection improvements at Aerospace Parkway and Raytheon Parkway will be included.
Construction Schedule: November 5, 2017 to March 30, 2018

Phase 2
Phase 2 Status: In construction
Phase 2 construction consists of 1.5 miles of roadway widening from two travel lanes to four, including intersection improvements at Nogales Highway and widening of the Union Pacific Rail Road crossing.
Planned construction start: April 1, 2018