    Total Actual Cost: $953,413
    Project Number:  CTR.4TTCLV
    Funding Sources: 1997 HURF Bonds, County HURF
    Completion Date: March 2018 
    Managing Dept.: Transportation
    Project Map: GIS Map

    The original project was approved by voters in the 1997 HURF bond election to widen existing Thornydale Road from two-lanes to four-lane divided cross section with raised landscape median, outside curbs, multi-use lanes, storm drains, landscaping, noise mitigation and screening adjacent to residential areas where warranted.

    The objective was to reduce traffic congestion and enhance safety along Thornydale Road.

    The project design was completed; however; construction start was delayed due to lack of funding which placed the project out of the five-year plan.

    The project has been replaced by a new project to resurface Thornydale Rd., CTR.4TCFLV, with reduced scope.  The remaining funds were transferred to the new project.