  • DOT to perform pavement preservation work on 1st Avenue: River Road to Ina Road

    Apr 21, 2017 | Read More News
    Share this page
    potholesStarting Monday, April 24 between the hours of 6 a.m. to 6 p.m., the Pima County Department of Transportation along with its contractor, VSS International, will crack seal and perform a micro seal surface treatment on 1st Avenue from River Road to Ina Road.

    The following is the contractor's anticipated work schedule:
    • Monday, April 24 through Monday, May 1: Crack seal and patch the roadway.
    • Tuesday, May 2 through Thursday, May 4: Micro seal the roadway.
    • Tuesday, May 9 through Thursday, May 11: Perform another micro seal treatment to the roadway.
    During this roadwork, motorists can expect lane restrictions, reduced speed and minor delays. Flaggers and a pilot car will assist traffic through the work zone. In the event of mechanical failure or inclement weather, the construction schedule is subject to change.

    This project is part of the Pavement Preservation Program for the fiscal year of July 1, 2016 through June 30, 2017. For a complete listing of the program, please visit PCDOT's website