  • FC5.02 Green Valley Erosion Control

    Total Actual Cost: $1,438,094
    Project Number: CFC5GVERC
    Funding Sources: 2004 General Obligation Bonds & Other Funding
    Completion Date: January, 2011
    Managing Dept.: Regional Flood Control District
    Project Map: GIS Map

    The project provided drainage improvements to control flooding and erosion in drainage ways located in Green Valley, Arizona. Drainage improvements were preformed in drainage ways 1, 3, 6, 7, 9, 13, 17, 24, and 25. The improvements ranged from filling scour holes with rip-rap and repairing existing structures to the construction of new bank protection and grade control structures.

    In addition to the improvements, the District also conducted the Green Valley 2010 Drainage Way Evaluations to reassess the original RS Engineering May 2004 report and to update the maintenance and engineering improvements needed for Green Valley.
    Green Valley Erosion Control
    Drainage Way 17 - New maintenance ramp.
    Green Valley Erosion Control
    Drainage Way 7 - New grade control structure, bank protection, spillways and repair of existing rock and rail bank protection.
    Green Valley Erosion Control
    Drainage Way 24 - New bank protection at confluence with Santa Cruz River.