    Total Actual Cost: $1,010,000
    Project Number: CFMBSCPM3
    Funding Sources: 1997 General Obligation Bonds
    Completion Date: January 2011
    Managing Dept.: Facilities Management
    Project Map: GIS Map

    The purpose of the project is to build additional courtrooms on the 8th floor. During this phase, an architectural design team did various portions of the design necessary to relocate several departments within the Superior Courts. Several relocations of smaller departments associated with the project were also accomplished.

    The design team also worked with the Superior Courts staff to program the courtrooms and associated spaces on the 8th floor and a small portion of the 7th floor. The construction documents have been completed under a different project and are currently ready for bidding.

    The design team did extensive programming with representatives of the departments to determine specific space needs. Facilities Management identified space on the first and second floors of the Admin West Building as the best place to locate the two largest departments that need to be moved from the 8th floor. The design team developed the space plan into construction documents that are currently being used to construct the new spaces.