  • DOT-57 Motor Pull-Outs and Concrete Work

    Total Actual Cost: $76,203
    Project Number:  CTR4MPPOC
    Funding Sources: 1997 HURF Bonds 
    Completion Date: June, 2015 
    Managing Dept.: Transportation
    Project Map: None

    This project was approved In response to recommendations from the Road Safety Assessment for Palo Verde Road, and information from an assessment of a crash site on River Road near La Cholla Blvd.

    Safety improvements included concrete pullouts at locations on Ina Road, Palo Verde Road and River Road. Pedestrian curb openings on Palo Verde Road were built and improvements were made to improve access control near River Road and La Cholla Blvd.