  • DOT-41 & DOT-57 Pavement Preservation Projects FY2014

    Total Actual Cost: $ 6,366,668
    Project Number: CTR4PPP14
    Funding Sources: 1997 HURF Bonds, County HURF, Other 
    Completion Date:  Nov 2014
    Managing Dept.: Transportation Dept.
    Project Map: GIS Map
     
    A total of 29 miles of roadway were preserved with this project. A variety of pavement preservation methods were used depending on the condition of the existing pavement including: chip seal, mill and fill, and structural overlay. It included $1.7M of work in District 2 funded with DOT-41 HURF Bonds.