  • DOT-41 Julian Wash: I-10 to Campbell: Ramps

    Total Actual Cost: $310,629
    Project Number: CTR4JLRMP 
    Funding Sources: 1997 HURF Bonds, General Fund, Other
    Completion Date: November 2014
    Managing Dept.: Pima County Project Management Office
    Project Map: GIS map

    This project was designed in phases and delivered as three separate sub-projects:, 4JLRMP, 4JLWST and 4JLMID. The project was a public/private partnership with external funding provided by the TMC/Carondelet Healthcare Foundation. This funding strategy greatly multiplies local funding opportunities providing added benefits to the finished greenway project.  The Foundation provided an additional $1,907,000 to the total cost of the new multiuse path.

    Improvements include the ramps between Campbell and Alvernon to separate Loop users from the roadway cross traffic. The ramps were designed to use existing box culverts, and were placed to reduce impacts to the wash. Connections were built between the Loop and roadway bike lanes. The longer culverts were lighted for daytime use.
    A grand opening event was held November 1, 2014, and included a special health fair in participation with our foundation partners.

    julian Wash RAMPS 1of2 Julian Wash RAMPS 2of2