  • DOT-57 Safety Management Systems & Program Development

    Total Actual Cost: $819,505
    Project Number: CTR4SMSPD 
    Funding Sources: 1997 HURF Bonds; Federal, state, and local funds 
    Completion Date: June 2014
    Managing Dept.: Transportation
    Project Map:

    This project entailed preparation of the annual update of the Safety Management System Program Report. This report analyzes crashes occurring on County roadways and prioritizes safety improvements. Generally the construction of a safety improvement project is done separately. However, there were some minor improvements included in this project, such as adding loop detection or turning lanes to intersections in order to improve safety and traffic flow.

    The prioritized project list produced in the annual Safety Management System Report is an important tool for project selection so that the Department can spend safety money wisely.

    dot 57 ctr4hdbpeDOT57 Safety Management Systems

    Follow UsShare or bookmark this page

    Pima County Bonds

    (520) 724-8450


    Department Home
    Bond News
    Department Directory
    Feedback
    Boards, Commissions and Committees